Rubb, Inc. New Welding Shop Construction – Week 6
June 30th, 2008 by GlenWork on the building this week was minimal as only a skeleton crew was assigned to construction. In Thursday’s time-lapse video (to the right), the camera was reset to its default position from a thunderstorm the night before, and then repositioned mid-morning. You can see the gable endwall steelwork being fitted into place until late morning, and a few passing showers in the afternoon.